Notifications
Clear all
Topic starter
26/08/2022 3:25 am
A customer has two HPE Nimble arrays that are replication partners. The replication schedule is set to every hour
After the replication completed at 1 00 pm. the array at the primary site suffers a power failure at 1:30(pm Applications were failed over successfully by me administrators, and production continued on the secondary site array as designed Power was restored to the primary site array at 3:00 pm
When the administrator restores the replication to the primary site, which data Is sent to the primary array?
- A . all data that was changed al the secondary site from the last snapshot at 1:00 pm
- B . all data at the secondary site from the first snapshot on the array
- C . the data '"at was changed between 3:00 pm and the end of the snapshot replication
- D . the data that was changed between 1:30 pm and 3:00 pm at the secondary site
Suggested Answer: D