Universal Containers wants to schedule deliveries using Salesforce Field Service. Each delivery requires that an installation and safety inspection be performed by different Technicians during the same day. The safety inspection needs to be executed after the installation is complete.

How should the Consultant use Complex Work to meet this requirement?

  • A . Define Same Resource and Same Start dependencies.
    B. Define Start After Finish and Same Day dependencies.
    C. Define a Start After Finish dependency.
    D. Define a Same Start dependency.

Show Answer Hide Answer

Suggested Answer: B
 