How should a Consultant configure the Scheduling Policy to ensure a 30-minute lunch break that begins every day after 1pm?

1 Posts
1 Users
0 Likes
80 Views
(@ferronigiovanni)
Posts: 731
Noble Member
Topic starter
 

Universal Containers does not want the lunch break to interfere with existing scheduled work.

How should a Consultant configure the Scheduling Policy to ensure a 30-minute lunch break that begins every day after 1pm?

  • A . Create a recurring Service Appointment
    B. Create Resource Absences every day.
    C. Use appropriate Resource Operating Hours.
    D. Use the Resource Availability Rule.

Show Answer Hide Answer

Suggested Answer: A
 
Posted : 27/01/2023 4:22 am