DRAG DROP

You need to implement versioned changes to the integration pipelines. The solution must meet the data integration requirements.

In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.

Show Answer Hide Answer

Suggested Answer:

Explanation:

Graphical user interface, application

Description automatically generated

Scenario: Identify a process to ensure that changes to the ingestion and transformation activities can be version-controlled and developed independently by multiple data engineers.

Step 1: Create a repository and a main branch

You need a Git repository in Azure Pipelines, TFS, or GitHub with your app.

Step 2: Create a feature branch

Step 3: Create a pull request

Step 4: Merge changes

Merge feature branches into the main branch using pull requests.

Step 5: Publish changes

 