An organisation is assessing risks so it can prioritize its mitigation actions.
Following are the risks and their probability and impact:
Which of the following is the order of priority for risk mitigation from highest to lowest?
- A . A, B, C, D
- B . A, D, B, C
- C . B, C, A, D
- D . C, B, D, A
- E . D, A, C, B
Suggested Answer: A