According to the Capability Maturity Model Integration (CMMI), which of the following levels is identified by a managed process that is tailored from the organization's set of standard processes according to the organization's tailoring guidelines?

  • A . Level 0: Incomplete
  • B . Level 1: Performed
  • C . Level 2: Managed
  • D . Level 3: Defined

Show Answer Hide Answer

Suggested Answer: D

   