Which of the follow...
 
Notifications
Clear all

Which of the following should the audit manager do FIRST?

1 Posts
1 Users
0 Likes
86 Views
(@ruleychuck)
Posts: 689
Noble Member
Topic starter
 

The due date of an audit project is approaching, and the audit manager has determined that only 60% of the audit has been completed.

Which of the following should the audit manager do FIRST?

  • A . Determine where delays have occurred
    B. Assign additional resources to supplement the audit
    C. Escalate to the audit committee
    D. Extend the audit deadline

Show Answer Hide Answer

Suggested Answer: A
 
Posted : 08/02/2023 7:36 pm

Latest ISACA CISA Dumps Valid Version

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Share: