The due date of an audit project is approaching, and the audit manager has determined that only 60% of the audit has been completed.
Which of the following should the audit manager do FIRST?
- A . Determine where delays have occurred
B. Assign additional resources to supplement the audit
C. Escalate to the audit committee
D. Extend the audit deadline
Suggested Answer: A