Which of the following should be an IS auditor's GREATEST consideration when scheduling follow-up activities for agreed-upon management responses to remediate audit observations?
- A . Business interruption due to remediation
B. IT budgeting constraints
C. Availability of responsible IT personnel
D. Risk rating of original findings
Suggested Answer: D