Management receives information indicating a high level of risk associated with potential flooding near the organization's data center within the next few years. As a result, a decision has been made to move data center operations to another facility on higher ground.
Which approach has been adopted?
- A . Risk avoidance
B. Risk transfer
C. Risk acceptance
D. Risk reduction
Suggested Answer: A