For a particular sales order item, you have the following:

1 Posts
1 Users
0 Likes
84 Views
(@tsuchiuramanual)
Posts: 747
Noble Member
Topic starter
 

You have implemented Product Cost by Sales Oder in conjunction with cost-based POC results analysis in your organization.

For a particular sales order item, you have the following:

Plan revenue = 3000; Plan costs = 2000

Actual revenue = 1200; Actual cost=1000

What data does the system calculate during results analysis?

  • A . "Revenue = 1500; Cost of sales = 1000; Revenue surplus =300"
    B. "Revenue = 1200; Cost of sales = 1000; Capitalized revenue (revenue in excess of billings) = 200"
    C. "Revenue = 1500; Cost of sales = 1000; Capitalized revenue (revenue in excess of billings) = 300"
    D. "Revenue = 1200; Cost of sales = 1000; Revenue surplus =200"

Show Answer Hide Answer

Suggested Answer: C
 
Posted : 25/01/2023 12:58 am