Where can you maintain the planned delivery time used for scheduling in material requirements planning? Note: There are 3 correct Answers to this question.
- A . Purchasing info record
B. Outline agreement
C. Plant parameters
D. Material
E. Supplier
Suggested Answer: A, D, E