Where can you assign the release creation profile that is used to generate delivery schedules? Note: There are 2 correct Answers to this question.
- A . Scheduling agreement header
B. Supplier master
C. Material master
D. Scheduling agreement item
Suggested Answer: B, D
Posted : 15/11/2022 7:53 am