What are the consequences when you assgn a planned order to a production line manually, using the planning table in repetitive manufacturing?
- A . The planed order's component availability is checked.
B. The planed order is converted to production order.
C. The planned order's components are copied to the picking list.
D. The planed order generates capacity requirements
Suggested Answer: D