The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100%.
Which date is relevant for the calculation of future planned dates if the maintenance work is delayed?
- A . Technical completion date of the maintenance order
B. Date of the final time confirmation
C. Planned end date of the maintenance order
D. Planned date of the next call, independent of maintenance orderdates
Suggested Answer: A