How can a product be acquired after a material requirements planning run? There are 2 correct answers to this question. Note: Answers to this question are not verified by our experts, please study yourself and select the appropriate answers. Contribute: Please send the correct answers with reference text/link on
- A . Using a consignment issue order
B. Using a planned order
C. Using a purchase requisition
D. Using a service order
Suggested Answer: A,B