What are key activitiesof the Prepare phase of the SAP Activate methodology? Note: There are 3 correct answers to this question.
- A . Project setup
B. Customer self-enablement
C. Data migration
D. Starter system provisioning
E. User training
Suggested Answer: A,B,D