In what scenario will there be multiple resource requests for the same project role?

1 Posts
1 Users
0 Likes
75 Views
(@cornadante)
Posts: 716
Noble Member
Topic starter
 

In what scenario will there be multiple resource requests for the same project role?

  • A . Multiple skills have been assigned to the same project role.
    B. The resource assigned to the work package consists of multiple individual employees.
    C. Multiple work items have been created for the same project role.
    D. The estimated effort for the project role exceeds the work package duration.

Show Answer Hide Answer

Suggested Answer: C
 