You are working on a mid-range plan that spans the seasonal peak and you are evaluating the need for additional crewing.
Which of the following parameters can you model to plan production with extra shift(s)?
- A . Incremental production values
B. Capacity expansion with additional costs
C. Production source validity at the start of seasonal peak
D. Adjusted production interactive values
Suggested Answer: B