How many different time levels can be selected within one planning view?
- A . All time levels available in the time profile
- B . All time levels available in the time profile, restricted by global configuration parameter
- C . Only time levels from the base planning level of selected key figures
- D . Only base time levels of the planning area
Suggested Answer: B