A company has a work order with 50 separate tasks and 40 of the tasks have been completed. The company would like the remaining 10 tasks grouped with a new parent work order.
Which option will group the tasks?
- A . Select the task work orders and Create Work Package.
- B . Select the task work orders Create Job Plan from Work Plan.
- C . Create a new work order and add the task work orders on the Plans tab.
- D . Create a new work order and add the child work orders on the Plans tab.
Suggested Answer: A