What are the correc...
 
Notifications
Clear all

What are the correct sequence values to use on the Job Plan Sequence tab?

1 Posts
1 Users
0 Likes
232 Views
(@rickielewis)
Noble Member
Joined: 2 years ago
Posts: 713
Topic starter  

Maintenance is required on an asset at every 6,000 miles that uses job plan JP6K, and there is an additional Job Plan, JP18K, that is used at every 18,000 miles. This Meter-Based Frequency PM has a frequency of 6,000 miles.

What are the correct sequence values to use on the Job Plan Sequence tab?

  • A . JP6K = 1 JP18K = 2
  • B . JP6K = 1 JP18K = 3
  • C . JP6K = 0 JP18K = 3
  • D . JP6K = 6 JP18K = 18

Show Answer Hide Answer

Suggested Answer: B

   
Quote

Latest IBM C2010-555 Dumps Valid Version

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Share: