A company wishes to configure Maximo so that meter readings automatically create work orders based on condition monitoring points. The company has already configured the system in Organizational settings and created the appropriate condition monitoring points.
What additionally needs to be configured for this be accomplish?
- A . Any meter should be added to the asset and the ConditionMonWoGenCronTask should be active e
- B . A continuous type meter should be added to an asset and the PMWOGenCronTask should be active.
- C . A gauge type meter should be added to an asset and the MeasurePointWoGenCronTask should be active.
- D . A characteristic type meter should be added to an asset and the ConditionMonWoGenCronTask should be active.
Suggested Answer: C