Which of the following should be updated before requesting approval again?

1 Posts
1 Users
0 Likes
158 Views
 Tuan
(@shippertuan)
Posts: 713
Noble Member
Topic starter
 

A change advisory board did not approve a requested change due to the lack of alternative actions if implementation failed.

Which of the following should be updated before requesting approval again?

  • A . Scope of change
    B. Risk level
    C. Rollback plan
    D. End user acceptance

Show Answer Hide Answer

Suggested Answer: C
 