Which artifact shows a series of areas representing the amount of work in the different Kanban states?

1 Posts
1 Users
0 Likes
197 Views
(@ferronigiovanni)
Posts: 731
Noble Member
Topic starter
 

Which artifact shows a series of areas representing the amount of work in the different Kanban states?

  • A . Lead time diagram
    B. WIP Limits
    C. Burnup chart
    D. Cumulative Flow Diagram

Show Answer Hide Answer

Suggested Answer: D
 