A program manager evaluates conflicting stakeholder demands associated with cost, schedule, and intended benefits. The implementation team has a strong interest in cost and schedule, and a limited interest in the benefits being produced. The client is only focused on benefits.
Which of the following actions should the program manager take?
- A . Focus on the internal stakeholders to ensure cost and) schedule objectives are achieved
B. Balance stakeholder needs through the use of trade-offs among the stakeholder groups
C. Focus on the external stakeholders to ensure the intended benefits are achieved
D. Conduct a stakeholder meeting to allow everyone to state their priorities
Suggested Answer: D