A country is in the process of strengthening its defense program. A key project is not meeting its specified performance objectives. The project manager initiates a change request to address this issue.
What should the program manager do NEXT?
- A . Consider the option to close out the key project
B. Evaluate the program and re-baseline the objectives
C. Assess the benefits and impact to the program.
D. Amend the risk register with the key project changes
Suggested Answer: C