During the execution phase of a program a stakeholder complains to the program manager that they did not receive critical communications about one of the component projects What should the program manager do to address the situation'?
- A . Review and update the detailed stakeholder list
B. Review and update the stakeholder engagement plan
C. Execute the component project's communications management plan
D. Update the risk register.
Suggested Answer: B