Which two statements are correct when four teams are working on one single product?

1 Posts
1 Users
0 Likes
116 Views
(@pesterfieldrayford)
Posts: 681
Noble Member
Topic starter
 

Which two statements are correct when four teams are working on one single product?

  • A . There can be only one Product Owner.
    B. There can be only one Product Backlog.
    C. There can be 4 Product Owners.
    D. There can be 4 Product Backlogs.

Show Answer Hide Answer

Suggested Answer: A,B

Explanation:

1 Product = 1 Product Owner, 1 Product Backlog
 