Which of the following topics can be part of the Sprint Retrospective?

1 Posts
1 Users
0 Likes
109 Views
 Man
(@shortinoman)
Posts: 733
Noble Member
Topic starter
 

Which of the following topics can be part of the Sprint Retrospective?

  • A . Plan the next Sprint.
    B. Discuss the way the Team has communicated in the last Sprint.
    C. Discuss the way the Development team has collaborated with the Product Owner.
    D. Refine Product Backlog items.

Show Answer Hide Answer

Suggested Answer: B,C

Explanation:

Refinement can be done during the Sprint but not in the Retrospective. The next Sprint is planned in the Sprint Planning not in the Retrospective.
 