Which of the following actions should a Scrum Master do to start a new Project?
- A . Ensure that the developers have access to the systems.
B. Ask the Product Owner to explain the project, general requirements, project history and context.
C. Ask the team lead to explain the product roadmap.
D. Assign the first tasks to the Developers.
Suggested Answer: B
Explanation:
There are no team leads in scrum. The team is self-organizing, no one assigns tasks to the developers.
Explanation:
There are no team leads in scrum. The team is self-organizing, no one assigns tasks to the developers.