When is it time to integrate/deploy the developed code?

1 Posts
1 Users
0 Likes
139 Views
 Chi
(@jamiesonchi)
Posts: 727
Noble Member
Topic starter
 

When is it time to integrate/deploy the developed code?

  • A . At the end of the Sprint.
    B. Frequently / when ever possible.
    C. Before the release.

Show Answer Hide Answer

Suggested Answer: B

Explanation:

Scrum promotes continuous integration.
 