What are typical inputs for the Sprint Planning meeting?
- A . The Product Backlog.
B. The Sprint Scope recommended by the Scrum Master.
C. The projected capacity of the Development Team during the Sprint.
D. The baseline for the Sprint Backlog provided by the stakeholders.
E. The latest product Increment.
F. The past performance of the Development Team.
Suggested Answer: A,C,E,F
Explanation:
The input to the Sprint Planning meeting is the Product Backlog, the latest product Increment, projected capacity of the Development Team during the Sprint, and past performance of the Development Team. The number of items selected from the Product Backlog for the Sprint is solely up to the Development Team.
Explanation:
The input to the Sprint Planning meeting is the Product Backlog, the latest product Increment, projected capacity of the Development Team during the Sprint, and past performance of the Development Team. The number of items selected from the Product Backlog for the Sprint is solely up to the Development Team.