Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

1 Posts
1 Users
0 Likes
216 Views
 Theo
(@baintheo)
Noble Member
Joined: 1 year ago
Posts: 705
Topic starter  

Who determines when it is appropriate to update the Sprint Backlog during a Sprint?

  • A . The Project Manager.
  • B . The Development Team.
  • C . The Scrum Team.
  • D . The Product Owner.

Show Answer Hide Answer

Suggested Answer: B

   