Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?
- A . It is a complete list of all work to be done in a Sprint.
- B . Every item has a designated owner.
- C . Each task is estimated in hours.
- D . It is the Development Team's plan for the Sprint.
- E . It is ordered by the Product Owner.
Suggested Answer: D