How much time is required after a Sprint to prepare for the next Sprint?

1 Posts
1 Users
0 Likes
248 Views
 Coy
(@millotcoy)
Noble Member
Joined: 2 years ago
Posts: 688
Topic starter  

How much time is required after a Sprint to prepare for the next Sprint?

  • A . The break between Sprints is time-boxed to 1 week for 30 day Sprints, and usually less for shorter sprints.
  • B . Enough time for the requirements for the next Sprint to be determined and documented.
  • C . Enough time for the Development team to finish the testing from the last Sprint.
  • D . None. A new Sprint starts immediately following the end of the previous Sprint.
  • E . All of the above are allowed depending on the situation.

Show Answer Hide Answer

Suggested Answer: D

   