How much of the Sprint Backlog must be defined during the Sprint Planning event?

1 Posts
1 Users
0 Likes
293 Views
(@rickielewis)
Noble Member
Joined: 2 years ago
Posts: 713
Topic starter  

How much of the Sprint Backlog must be defined during the Sprint Planning event?

  • A . Just enough tasks for the Scrum Master to be confident in the Development Team’s understanding of the Sprint.
  • B . The entire Sprint Backlog must be identified and estimated by the end of the Sprint
    Planning meeting.
  • C . Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.
  • D . Just enough to understand design and architectural implications.

Show Answer Hide Answer

Suggested Answer: C

   