How much of the Sprint Backlog must be defined during the Sprint Planning event?
- A . Just enough tasks for the Scrum Master to be confident in the Development Team’s understanding of the Sprint.
- B . The entire Sprint Backlog must be identified and estimated by the end of the Sprint
Planning meeting. - C . Enough so the Development Team can create its best forecast of what is can do, and to start the first several days of the Sprint.
- D . Just enough to understand design and architectural implications.
Suggested Answer: C