For the purpose of transparency, when does Scrum say a new increment of working software must be available?

1 Posts
1 Users
0 Likes
251 Views
(@mccroygalen)
Noble Member
Joined: 2 years ago
Posts: 739
Topic starter  

For the purpose of transparency, when does Scrum say a new increment of working software must be available?

  • A . After the acceptance testing phase.
  • B . Before the release Sprint.
  • C . Every 3 Sprints.
  • D . At the end of every Sprint.
  • E . When the Product Owner asks to create one.

Show Answer Hide Answer

Suggested Answer: D

   