For the purpose of transparency, when does Scrum say a new increment of working software must be available?
- A . After the acceptance testing phase.
- B . Before the release Sprint.
- C . Every 3 Sprints.
- D . At the end of every Sprint.
- E . When the Product Owner asks to create one.
Suggested Answer: D