A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to colocate.
What should the project manager do to keep the team performing as effectively as possible?
- A . Ask the project sponsor and executive stakeholders to encourage the team to maintain their performance,
- B . Transition the team from an agile approach to a predictive approach for better performance cantral.
- C . Provide the team with virtual collaboration software and training on the software to minimize disruption,
- D . Evaluate project performance and step in if performance decreases to. an unacceptable level,
Suggested Answer: C