15/07/2022 6:55 pm
A project manager is developing a project baseline schedule and has started to assign team members to the project activities according to their function .
What should the project manager do in this phase?
- A . Develop project onboarding guidelines for the team members assigned to the project.
- B . Ensure that a kick-off meeting is planned and invite relevant stakeholders to participate.
- C . Ensure that lessons learned are considered as part of the project schedule decomposition.
- D . Confirm that no conflicts exist in resource calendars with assigned activities on other projects.
Suggested Answer: D