Notifications
Clear all
Topic starter
16/07/2022 8:05 pm
A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.
How should the project manager handle this issue?
- A . Disregard these stakeholders since the relevant documents have been secured to execute this project.
- B . Update the stakeholder register and risk management plan.
- C . Update the stakeholder register and revise the stakeholder engagement plan.
- D . Explain to the community members why they were not included as stakeholders for the project.
Suggested Answer: C