A project is approaching its project closure phase, and the project manager receives an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.
Which three actions should the project manager ask the project specialist to take? (Choose three)
- A . Create a quality assurance plan for the documentation.
- B . Identify the components of the project documentation.
- C . Archive only the initial and draft versions of the documents.
- D . Ensure that the documents are in an easily retrievable form.
- E . Collect the documents at the time of their creation.
Suggested Answer: B,C,D