Notifications
Clear all
Topic starter
06/11/2022 3:42 pm
A project manager is managing a project that is halfway through its execution phase and the quality standards of the deliverables were formally accepted However, a government agency has recently Introduced new standards that may significantly impact the project. The deliverables must be changed to align with the new quality standards
What should the project manager do?
- A . Set up a structured, independent processes to determine if project activities followed the standards.
- B . Schedule training for the project team on the new regulations introduced by the government agency
- C . Evaluate the impact the new regulations will have on the project and submit a change request
- D . Update the lessons learned register and inform senior management of the new standards
Suggested Answer: C