Notifications
Clear all
Topic starter
A milestone task on the critical path has been completed.
Which of the following should the project manager notify?
- A . Owner of predecessor task
B. Project team
C. Project sponsor
D. Project steering committee
Suggested Answer: C
Posted : 29/10/2022 8:53 pm