Which of the following documents should the project coordinator use?

1 Posts
1 Users
0 Likes
117 Views
(@bulluckrolando)
Posts: 664
Noble Member
Topic starter
 

A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies.

Which of the following documents should the project coordinator use?

  • A . Risk register
    B. Issue log
    C. Communication plan
    D. Status report

Show Answer Hide Answer

Suggested Answer: A

Explanation:

References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 240
 