You are preparing to install a new cluster at a customer site.
Which two concerns must you address with the customer in this scenario? (Choose two.)
- A . Is there an uninterruptible power supply (UPS) system?
B. Is there enough rack space available?
C. Are the power requirements fulfilled?
D. Is there a fire extinguishing system?
Suggested Answer: AD