A customer requests a proposal for two HPE 3PAR arrays using asynchronous periodic replication. The customer has two data centers, and the current bandwidth available for replication between the data centers is 200 Mb/s.
The customer is replicating 30TB, and the change rate is 3% in 24 hours. The customer wants to achieve an RPO of 10 minutes.
Which statement about bandwidth and replication is true for the customer requirements?
- A . The bandwidth is sufficient, and replication must happen every 5 minutes
- B . The bandwidth will have to be increased, and replication must happen every 5 minutes
- C . The bandwidth is sufficient, and replication must happen every 10 minutes
- D . The bandwidth will have to be increased, and replication must happen every 10 minutes
Suggested Answer: B