Notifications
Clear all
Topic starter
30/09/2022 9:47 pm
A customer has two HPE Nimble arrays that are replication partners. The replication schedule is set to every hour.
After replication completed at 1:00pm, the array at the primary site suffers a power failure.
Applications were failed over successfully by the administrators, and production continued on the secondary site array as designed.
At 3:00pm, the power was restored to the primary site array.
What does the administrator need to do first to restore services in the primary site?
- A . Perform handover from the secondary array to the primary array
- B . Create a new replication partnership from the primary array to the secondary array
- C . Create a new replication partnership from the secondary array to the primary array
- D . Perform a failback of the existing replication partnership to the primary array
Suggested Answer: A