A project requires the management system to access a third-party generator set, two smart meters 1 (same model), and two precision air conditioners (same model), then the management system needs to report ( ) a third-party equipment access fee? ( )

1 Posts
1 Users
0 Likes
83 Views
(@schultzachariah)
Posts: 745
Noble Member
Topic starter
 

A project requires the management system to access a third-party generator set, two smart meters 1 (same model), and two precision air conditioners (same model), then the management system needs to report ( ) a third-party equipment access fee? ( )

  • A . 1
    B. 3
    C. 5
    D. None of the above is true

Show Answer Hide Answer

Suggested Answer: B
 