in order forthe IT manager in cnarge of a company's disaster recovery plan to have complete planning documentation, he should ensure that the documentation includes all of the following except

1 Posts
1 Users
0 Likes
219 Views
(@pochethurman)
Posts: 704
Noble Member
Topic starter
 

in order forthe IT manager in cnarge of a company's disaster recovery plan to have complete planning documentation, he should ensure that the documentation includes all of the following except

  • A . the results of the latest disaster recovery test run
    B. the phone numbers of key employees
    C. vendors who win set up the hot site
    D. program and operating system documentation

Show Answer Hide Answer

Suggested Answer: C
 