From an IS auditor's perspective, which of the following would be the GREATEST risk associated with an incomplete inventory of deployed software in an organization?

1 Posts
1 Users
0 Likes
136 Views
 Chas
(@heddinschas)
Posts: 712
Noble Member
Topic starter
 

From an IS auditor's perspective, which of the following would be the GREATEST risk associated with an incomplete inventory of deployed software in an organization?

  • A . Inability to close unused ports on critical servers
    B. Inability to identify unused licenses within the organization
    C. Inability to deploy updated security patches
    D. Inability to determine the cost of deployed software

Show Answer Hide Answer

Suggested Answer: C
 